Aanpak 1/2
QuickScan
- Site visit
- High level risk assessment
of:
• Grid congestion and grid
connection
• Spatial constraints
• Environmental constraints
• Insurance aspects - Map/Plan of site
- Nearby infrastructure
Initial Design & Feasibility
- Data collection
- Initial design
• PV Plant Layout
• Capacity/Size
• Yield indication - Business Case
• CAPEX
• OPEX
• Revenue streams
• Sensitivity analysis - Business case and sensiti- vity analysis
Administrative procedures
- SDE++ application
- Discussions local authorities
- Drafting permits (construction + environmental)
- Permit application + follow up
- Drafting grid connection application
- Grid connection application + follow up
Tender
- Drafting tender documents
• Tender procedures
• RfI
• RfQ - Manage contractors’ site inspections
- Analysis of offers
- Contract negotiations with suppliers/contractors
- Shortlisting & BAFO
- Contracting
Project management
- Project management
- Progress meetings
- Site visits & quality checks
- Technical support client
- Stakeholder management
- Support/Manage 3rd parties
- Design verification
- Manage FAT & SAT
- Milestone control
Commissioning & Acceptance
- Commissioning procedure (incl. witnessing)
- Provisional acceptance
- (Final acceptance)
- Acceptance certificates